Here we have answered the most common questions people ask before choosing a liquid flow screed. If you have a question that hasn’t been answered here, please contact us.
On average, for the ground floor of any house, 2 days. This includes all preparation.
After the first fix plumbing is complete, and the build is watertight.
With underfloor heating, 45mm. Without underfloor heating, 35mm.
The floor will be suitable for light impact foot traffic after 48 hours, and you can install partition walls, kitchens etc. after a week.
Screed dries at a rate of 1mm per day for every mm of thickness up to 50mm of thickness and tiling can be done once the screed is completely dry. If you tile when there is still moisture in the screed, the tiles will not bond with the adhesive.
Cookie | Duration | Description |
---|---|---|
cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |